| Project | Requirements for parameters | |
| Installation site | First Mine Yangpo Weir | |
| Installation date | 2014.8 | |
| Operation time | 21 months | |
| Rated voltage | 35/6.3kV | |
| Number of high-voltage phases | Three-phase | |
| Number of low-voltage phases | Three-phase | |
| Rated capacity kVA | 2000 | |
| High-voltage tapping scope % | ±2×2.5 | |
| Rated current A | 33/183.3 | |
| Rated frequency Hz | 50 | |
| Coupling group | Yd11 | |
| No-load loss W | 4230 | |
| Load loss W | Level F(120℃) | 18200 |
| Total loss W | Level F(120℃) | 22430 |
| No-load current % | 0.75 | |
| Short-circuit impedance % | 7.2 | |
| Noise level dB | 55 | |
| Cooling mode | ANAF | |
| Voltage regulating mode | No excitation voltage adjustment | |
©1996-2017 晋ICP备07500050号 Huaxin Copyright
©2016-2017 晋ICP备07500050号 Huaxin Copyright